2020 Forcemain Project
Updates
11/9/2020
Upcoming Work (Next Two Weeks)
Upcoming Work (Next Two Weeks)
- Continue 24” force main installation with 2 crews. Third crew possibly next week for culverts or 10” work.
- Will coordinate with Drain commission and give anticipated date when approaching culverts at 46+00. They want to upsize 24” to 42”; Discussed and approved after potholing to move 10” to other side (east side) of box culvert. Separate e-mail sent for contractor to protect box culvert. County Drain will start work as early as tomorrow. After meeting next day, they started and determined to wait until 10” is rerouted by us. Plan now is for that work to take place next week pending weather.
10/07/2020
Upcoming Work (Next Two Weeks)
1. Continue 24” force main instillation down Huddle Road. 1 more crew to be added next week, with the potential for a 3rd crew following. Requested staking 29+00 to 45+00 and 81+00 to 106+00, 5+00 to 29+00 previously staked.
2.Air release structures will be installed as they approach them. 2nd crew to start at air release #4 station 65+00
3.Will coordinate with Drain commission and give anticipated date when approaching culverts at 46+00.
Upcoming Work (Next Two Weeks)
1. Continue 24” force main instillation down Huddle Road. 1 more crew to be added next week, with the potential for a 3rd crew following. Requested staking 29+00 to 45+00 and 81+00 to 106+00, 5+00 to 29+00 previously staked.
2.Air release structures will be installed as they approach them. 2nd crew to start at air release #4 station 65+00
3.Will coordinate with Drain commission and give anticipated date when approaching culverts at 46+00.